OUR PROJECTS
Take a look at what we are working on. Click below and view our current projects.
Feel free to leave a comment at the bottom of the page. Click on the button below to view our 'Previously Completed Projects'

Dickinson Substation Expansion Construction
The Dickinson Substation Expansion Construction project is being constructed for Basin Electric Power Cooperative. Construction is scheduled to start on or around 6/1/2020, with a completion of 6/30/2021.

North Loup Substation

True Red Wing Substation Cap Bank Addition
Highmark Erectors, Inc. will be performing a capacitor bank addition for the True/Red Wing Substation. Work on this project will start in November of 2020 and be wrapped up by the end of the year.

Moccasin Creek Substation
The Moccasin Creek Substation has been contracted to Highmark Erectors, Inc. The Moccasin Creek Substation is located about 7 miles south of Mandaree, ND. Scopes of work with this contract include foundation installation. All other work will use time & material rates.
Norfolk Substation Modifications
Westhill Breaker Replacement
Gerald Gentleman Station
Highmark Erectors, Inc. will be adding a 345kV bay to the Gerald Gentleman Station for Nebraska Public Power District. Construction completion is estimated on or around 2/1/2021.

Richmond Substation
Highmark Erectors, Inc. will be constructing the new Richmond Substation for East River Electric Cooperative. The project is located west of Aberdeen SD. Construction will start in Oct. of 2020 and be completed by June of 2021.

Miles City SW Transmission Substation

Marshal Substation
Highmark Erectors, Inc. will be performing work at the Marshal Substation for East River Electric Cooperative. Work will start in the spring to summer of 2020 and be completed by 1/5/2021.

Lewis & Clark Transmission Substation Addition
Highmark Erectors, Inc. will be performing work in the Lewis & Clark Transmission Substation for Montana-Dakota Utilities. Construction will start in July of 2020, with phase 1 completing around 10/10/2020. Phase 2 will start around 3/1/2021 and complete about July 2021.

Bismarck Sweet Ave Substation

Koch Substation Circuit Switcher Replacement

Sauk Prairie Substation
Burke-Divide Electric Cooperative, Inc. has contracted Highmark Erectors, Inc. to construct the new Sauk Prairie Substation will start in mid-June of 2020 with a tentative completion of 10/31/2020. The demo of the Greenbush Substation will happen after the energization of the Sauk Prairie Substation.

Koch Substation Capacitor Bank Additions
Highmark Erectors, Inc. will be performing a capacitor bank addition for the Koch Substation. Work on this project will start in November of 2020 and be wrapped up by the end of the year.

Rancho Substation Yard Expansion
Highmark Erectors, Inc. has been contracted to perform a yard expansion at the Rancho Substation for Tri-State Generation & Transmission. Construction will be completed around the end of Sept. 2020.
Divide Substation
North Penrose Substation
Highmark Erectors, Inc. will be performing work on the new North Penrose Substation for Black Hills Colorado Electric. Construction will start in the spring of 2021 and be completed by the middle of Oct. 2021.

Dayton Substation
Highmark Erectors, Inc. will be performing work on the Dayton Substation. Foundation and below grade work will start in the fall of 2020 with construction wrapping up by the summer of 2021.

Linton Substation
Our safety commitment far exceeds industry standards because we understand that in order to be successful, safety must be paramount.