Bear Creek 115kV Substation

The Bear Creek 115kV Substation consists of three distribution transformers.  There is one 115kV/15kV distribution structure with 2 feeds, and two 115kV/25kV distribution bays that route to a switchgear building.  This project will service a ONEOK gas plant that is located six miles north of Killdeer ND.  The scope of this project includes the installation of concrete foundations, grounding system, conduit system, erection of steel, all major equipment, rigid and strain bus system, wiring, addition of the road base to the subgrade, and the finish graded rock.  The project was started in October of 2015 and should be completed by the end of March 2016. 